(1) A responsible person may carry out independent remediation in accordance with the minister's regulations whether or not
(a) a determination has been made as to whether the site is a contaminated site,
(b) a remediation order has been issued with respect to the site, or
(c) a voluntary remediation agreement with respect to the site has been entered into.
(2) Any person undertaking independent remediation of a contaminated site must
(a) notify a director in writing promptly on initiating remediation, and
(b) notify the director in writing within 90 days of completing remediation.
(3) A director may at any time during independent remediation by any person
(a) inspect and monitor any aspect of the remediation to determine compliance with the regulations,
(b) issue a remediation order as appropriate,
(c) order public consultation and review under section 52 [public consultation and review], or
(d) impose requirements that the director considers are reasonably necessary to achieve remediation.
(4) On request of a person carrying out independent remediation and on receiving adequate information respecting the independent remediation, a director may
(a) review the remediation in accordance with the regulations and any requirements imposed under subsection (3) (d), and
(b) issue an approval in principle or a certificate of compliance under section 53 [approvals in principle and certificates of compliance].
(5) The director may assess against a person, in accordance with the regulations, the prescribed fees for carrying out the actions referred to in subsection (4).