Community Charter, SBC 2003, c. 26
Section 76
Time limit for compliance
Cite as Community Charter, SBC 2003, c. 26, s. 76 · read from BC Laws on November 17, 2026
The text
(1) The resolution imposing a remedial action requirement must specify the time by which the required action must be completed.
(2) Subject to section 79 [shorter time limits in urgent circumstances], the time specified under subsection (1) must not be earlier than 30 days after notice under section 77 (1) [notice to affected persons] is sent to the person subject to the remedial action requirement.
(3) The council may extend the time for completing the required action even though the time limit previously established has expired.
Read the Community Charter on BC Laws ↗