The text
(1) During the 60 days after a matter is settled under section 287 [final proposal arbitration] or 288 [full arbitration], the parties may agree on a settlement that differs from the decision of the arbitrator.
(2) At the end of the period referred to in subsection (1), unless agreement is reached as referred to in that subsection, the decision of the arbitrator becomes binding on the parties.
(3) If the decision becomes binding under subsection (2), the parties to the arbitration must adopt the bylaws and take the other actions required to implement the terms and conditions of the arbitrator's decision within 90 days after it becomes binding under that subsection.
(4) Despite any other provision of this Act or any other Act, approval of the electors or assent of the electors is not required for a bylaw referred to in subsection (3).
(5) A dispute resolution officer may extend the time period under subsection (1) before or after it has expired.