Budget Transparency and Accountability Act, SBC 2000, c. 23
Section 8
Major capital project information to be presented with the estimates
Cite as Budget Transparency and Accountability Act, SBC 2000, c. 23, s. 8 · read from BC Laws on November 17, 2026
The text
(1) Subject to subsection (5) and section 19 (5) [exception if disclosure would be harmful], for any project where the government reporting entity, directly or indirectly,
(a) has made commitments, or
(b) anticipates making commitments
that will, in total, exceed $125 million towards the capital cost of the project, the minister must present to the Legislative Assembly, at the same time that the main estimates are presented, a statement of the current and anticipated total cost to the entity in relation to the capital cost of the project.
(2) For the purposes of subsection (1), a commitment includes
(a) the amount of any money,
(b) the value of any land, facilities, rights or other benefits, and
(c) the amount of any guarantees,
contributed, made in respect of or otherwise provided, or anticipated to be provided, by the government reporting entity towards the capital cost of the project.
(3) The obligation under subsection (1) ends when no further cost to the government reporting entity in relation to the capital cost of the project is anticipated.
(4) [Repealed 2022-11-8.]
(5) Subsection (1) does not apply in respect of a commitment the government reporting entity, directly or indirectly, has made or anticipates making within 30 days before the date statements of cost are presented under subsection (1).
(6) The minister must
(a) review whether the amount referred to in subsection (1) is appropriate before the end of the 2035–2036 fiscal year and before the end of every tenth fiscal year following the previous review, and
(b) make public the results of that review.