Pulp and Paper Effluent Regulations, SOR/92-269
Section 13
Cite as Pulp and Paper Effluent Regulations, SOR/92-269, s. 13 · current to June 14, 2026 · regulation last amended June 4, 2026
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) Where less than three years of data are available on which to calculate the reference production rate of a mill, the operator may use a reference production rate calculated on the basis of available data or may apply to the authorization officer for an interim reference production rate.
(2) If the 90th percentile of the daily production of finished product at a mill has increased or is expected to increase by more than 25%, in respect of any period of 100 consecutive days, from the reference production rate of the mill, the operator may apply to the authorization officer for an interim reference production rate.
(3) If the 90th percentile of the daily production of finished product at a mill has decreased or is expected to decrease by more than 25%, in respect of any period of 100 consecutive days, from the reference production rate of the mill, the operator shall apply to the authorization officer for an interim reference production rate no later than 31 days after the decrease occurs or after becoming aware of the expected decrease, as the case may be.
(4) An applicant for an interim reference production rate shall submit plans, specifications and other information on the design and capability of the mill’s production process to the authorization officer and such further information as the authorization officer may subsequently require to assess the application.
(5) If, in accordance with subsection (1), (2) or (3), the authorization officer assigns an interim reference production rate to a mill to be used for the purposes of section 14 instead of the reference production rate, the interim reference production rate shall be based on an estimation of what the 90th percentile of the daily production would be at that mill. The estimation shall be based on the information submitted in accordance with subsection (4).
(6) The use of an interim reference production rate shall commence on the day the authorization officer may specify and expires at the end of the year.
Read the Pulp and Paper Effluent Regulations on the Justice Laws Website ↗
Made under Fisheries Act, R.S.C. 1985, c. F-14.
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.