Notice of Railway Works Regulations, SOR/91-103

Section 4

Cite as Notice of Railway Works Regulations, SOR/91-103, s. 4 · current to July 24, 2025 · regulation last amended March 22, 2006

Statute Watch

Get an alert when a bill in Parliament would change this section, and every time it moves.

The text

The notice referred to in section 3 shall (a) be given at least 60 days before the proposed date of commencement of the proposed railway works; (b) set out the period, not less than 60 days, during which objections, pursuant to subsection 8(2) of the Railway Safety Act, may be filed; and (c) contain the following information, namely, (i) a drawing showing the location of the proposed works, (ii) a description of the proposed works with general plans, including elevations of proposed structures, (iii) a description of any impact that the proposed works may have on the safety of persons and property, and (iv) the proposed date of commencement and the projected time for completion of the proposed works.
Read the Notice of Railway Works Regulations on the Justice Laws Website ↗

Made under Railway Safety Act, R.S.C. 1985, c. 32 (4th Supp.).

Bills in Parliament that would change this section 0

No bill we hold would amend or repeal this section.