Procurement Review Board Regulations, SOR/89-41
Section 23
Cite as Procurement Review Board Regulations, SOR/89-41, s. 23 · current to July 24, 2025 · regulation last amended March 22, 2006
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) Where the basis of a complaint is known or should reasonably have been known prior to bid opening or the closing date for receipt of bids, the complaint shall be filed prior to bid opening or the closing date for receipt of bids, as the case may be, but not later than 10 days after the basis of the complaint is known or should reasonably have been known.
(2) In any case other than those referred to in subsection (1), a complaint shall be filed not later than 10 days after the basis of the complaint is known or should reasonably have been known, whichever is earlier.
(3) Where a complaint has been filed initially with the government institution, any subsequent complaint filed with the Board within 10 days after actual or constructive knowledge of the denial of relief by the governmental institution shall be considered by the Board where the initial complaint to the governmental institution was filed within the time limits set out in subsection (1) or (2) or within such shorter time limits as may be required by the governmental institution in respect of that initial complaint.
(4) The Board, where good cause is shown or where it determines that a complaint raises issues significant to the procurement system, may consider any complaint that is not filed within the time limits set out in this section.
Read the Procurement Review Board Regulations on the Justice Laws Website ↗
Made under Canada-United States Free Trade Agreement Implementation Act, S.C. 1988, c. 65.
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.