Canada Occupational Health and Safety Regulations, SOR/86-304
Section 3.12
Cite as Canada Occupational Health and Safety Regulations, SOR/86-304, s. 3.12 · current to February 18, 2026 · regulation last amended March 26, 2025
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) Before the commencement of work on a tunnel, excavation or trench, the employer shall mark the location of all underground pipes, cables and conduits in the area where the work is to be done.
(2) Where an excavation or trench constitutes a hazard to employees, a highly visible barricade shall be installed around it.
(3) In a tunnel or in an excavation or trench that is more than 1.4 m deep and whose sides are sloped at an angle of 45° or more to the horizontal
(a) the walls of the tunnel, excavation or trench, and
(b) the roof of the tunnelshall be supported by shoring and bracing that is installed as the tunnel, excavation or trench is being excavated.
(4) Subsection (3) does not apply in respect of a trench where the employer provides a system of shoring composed of steel plates and bracing, welded or bolted together, that can support the walls of the trench from the ground level to the trench bottom and can be moved along as work progresses.
(5) The installation and removal of the shoring and bracing referred to in subsection (3) shall be performed or supervised by a qualified person.
(6) Tools, machinery, timber, excavated materials or other objects shall not be placed within 1 m from the edge of an excavation or trench.
Read the Canada Occupational Health and Safety Regulations on the Justice Laws Website ↗
Made under Canada Labour Code, R.S.C. 1985, c. L-2.
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.