Gas Pipeline Uniform Accounting Regulations, SOR/83-190
Section 30
Cite as Gas Pipeline Uniform Accounting Regulations, SOR/83-190, s. 30 · current to July 24, 2025 · regulation last amended March 16, 2020
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) For the purposes of these Regulations, additions to plant shall include
(a) increases in plant through purchase or construction of additional plant,
(b) the replacement of existing plant units, and
(c) the capitalization of major renewals to plantand, subject to the approval of the Commission, may include substantial improvements made to existing plant in order to make such plant more useful, more efficient, more durable or of greater capacity than the plant was when it was originally placed in service.
(2) The cost of additions referred to in subsection (1) shall be debited to the appropriate plant accounts.
(3) Typical elements of construction are set out in sections 16 to 27 and section 29.
(4) All expenditures relevant to new construction shall be capitalized.
(5) After the completion of initial construction, only the costs directly connected with additions or replacements of plant shall be capitalized.
(6) All property charged to plant accounts shall consist of plant units or minor items of plant.
Read the Gas Pipeline Uniform Accounting Regulations on the Justice Laws Website ↗
Made under N-7.
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.