Landfill Methane Regulations, SOR/2025-279

Section 23

Deferral

Cite as Landfill Methane Regulations, SOR/2025-279, s. 23 · current to December 29, 2025 · regulation last amended December 12, 2025

Statute Watch

Get an alert when a bill in Parliament would change this section, and every time it moves.

The text

(1) The Minister may, on the application of an owner or operator referred to in subsection 13(1) or an owner or operator of a landfill, as the case may be, defer a time limit set out in subsection 14(2) or 18(2) by no more than six months. (2) The application must be submitted to the Minister at least 45 days before the applicable time limit expires. It must include the reasons for the application and (a) in the case of the time limit set out in subsection 14(2), (i) the information referred to in subparagraphs 15(d)(i) to (iii), (ii) the expected date for the completion of the measures required to eliminate the methane leak and the reasons why it is the earliest feasible date to do so, and (iii) a description of what will be done to minimize methane emissions from the equipment component until the measures are completed; and (b) in the case of a time limit set out in subsection 18(2), (i) the information referred to in subparagraphs 21(g)(i) to (iii), (ii) the expected date for the completion of the measures required to eliminate the exceedance and the reasons why it is the earliest feasible date to do so, and (iii) a description of what will be done to minimize methane emissions until the measures are completed. (3) A deferral shall be granted if the Minister is satisfied that (a) the owner or operator’s inability to meet the applicable time limit is due to circumstances that are beyond the owner or operator’s control and that arise from (i) an outstanding provincial or territorial regulatory permit or approval, (ii) the delayed procurement, delivery or installation of necessary equipment, or (iii) conditions that pose a serious risk to human health or safety; and (b) the proposed measures to minimize methane emissions before expiration of the deferred time limit are adequate. (4) The Minister must revoke a deferral if the Minister has reasonable grounds to believe that the owner or operator has submitted false or misleading information to the Minister. (5) Before revoking a deferral, the Minister shall provide the owner or operator with written reasons for the proposed revocation and an opportunity to make written representations in respect of it.
Read the Landfill Methane Regulations on the Justice Laws Website ↗

Made under Canadian Environmental Protection Act, 1999, S.C. 1999, c. 33.

Bills in Parliament that would change this section 0

No bill we hold would amend or repeal this section.