(1) If an exceedance is detected, whether during a monitoring event or at any other time, the owner or operator of the landfill shall, within 30 days after the day on which the exceedance was first detected,
(a) confirm that the exceedance has been eliminated by measuring the methane concentration at the location of the exceedance using an instrument and method referred to paragraph 19(1)(a) or (c); or
(b) prepare a plan that includes
(i) the cause of the exceedance and a description of the measures required to eliminate it,
(ii) the expected date for the completion of the measures and the reasons why it is the earliest feasible date to do so, and
(iii) a description of what will be done to minimize methane emissions until the measures are completed.
(2) If the elimination of the exceedance is not confirmed in accordance with paragraph (1)(a), the owner or operator shall eliminate the exceedance within six months after the day on which it is first detected.
(3) An exceedance is considered to be eliminated
(a) in relation to a surface methane concentration, if the surface methane concentration where the exceedance was detected is less than 500 ppmv; and
(b) in relation to a zone-average surface methane concentration, if the zone-average surface methane concentration in the zone where the exceedance was detected is less than 25 ppmv.
Read the Landfill Methane Regulations on the Justice Laws Website ↗
Made under Canadian Environmental Protection Act, 1999, S.C. 1999, c. 33.