Canada Offshore Renewable Energy Regulations, SOR/2024-272
Section 66
Final report
Cite as Canada Offshore Renewable Energy Regulations, SOR/2024-272, s. 66 · current to December 2, 2025 · regulation last amended December 16, 2024
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
The operator must, within six months after the day on which all authorized work or activities related to the offshore renewable energy project or offshore power line are completed, submit to the Regulator a final report that includes the following information:
(a) a statement as to whether the work or activities were carried on as planned and as authorized;
(b) if the work or activities were not carried on as planned and as authorized, a description of the manner in which the carrying on of the work or activities deviated from what was planned and authorized; and
(c) a description of the state of the operations site as of the completion of all authorized work and activities.
Read the Canada Offshore Renewable Energy Regulations on the Justice Laws Website ↗
Made under Canadian Energy Regulator Act, S.C. 2019, c. 28, s. 10.
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.