Canada Offshore Renewable Energy Regulations, SOR/2024-272
Section 47
Change of certifying authority
Cite as Canada Offshore Renewable Energy Regulations, SOR/2024-272, s. 47 · current to December 2, 2025 · regulation last amended December 16, 2024
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) If the operator decides to replace the certifying authority with a new certifying authority, the operator must provide the name of the organization that the operator proposes to engage as the new certifying authority to the Regulator, along with a description of the organization’s qualifications to assume the responsibilities referred to in subsection 40(3).
(2) If the operator engages a new certifying authority before the initial certificate of fitness is issued, the new certifying authority must carry out its own independent assessment, monitoring, inspection, verification and validation activities for the purposes of issuing the certificate.
(3) If the operator engages a new certifying authority after a certificate of fitness has been issued, the operator must develop and submit to the Regulator a transition plan outlining all of the activities to be carried out by the parties before the transition from the former to the new certifying authority and demonstrating that the transition will not result in any gaps, delays or negative effects on the extent and quality of the activities referred to in subsection 40(3).
(4) The operator must ensure that the transition plan is implemented.
(5) There must be no more than one certificate of fitness and one certifying authority in relation to an offshore renewable energy project or offshore power line at any given time.
Read the Canada Offshore Renewable Energy Regulations on the Justice Laws Website ↗
Made under Canadian Energy Regulator Act, S.C. 2019, c. 28, s. 10.
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.