The text

(1) The certifying authority must prepare a plan for the periodic inspection of the facilities, equipment and systems related to the offshore renewable energy project or offshore power line during their construction and during their operation and maintenance and provide those plans to the Regulator. (2) The inspection plan must (a) include a schedule for the periodic review of the operator’s records from the management system to identify any changes to the management system that might affect safety, security or environmental protection; and (b) be updated as needed to ensure that the facilities, equipment and systems are inspected in light of those changes. (3) The certifying authority must establish the scope and frequency of the periodic inspections based on a risk assessment conducted in accordance with prevailing industry standards and best practices. (4) The certifying authority must, as soon as circumstances permit, inform the Regulator of any material changes to the inspection plan.
Read the Canada Offshore Renewable Energy Regulations on the Justice Laws Website ↗

Made under Canadian Energy Regulator Act, S.C. 2019, c. 28, s. 10.