Federal Prompt Payment for Construction Work Regulations (Dispute Resolution), SOR/2023-271
Section 22
Time limit for determination
Cite as Federal Prompt Payment for Construction Work Regulations (Dispute Resolution), SOR/2023-271, s. 22 · current to July 24, 2025 · regulation last amended December 9, 2023
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) Subject to subsection (2), the adjudicator must make a determination no later than 20 days after the day on which the response referred to in section 18 is received or, if there is no response, no later than 20 days after the day on which it was to be provided under that section.
(2) The time limit referred to in subsection (1) may be extended for up to five days by the adjudicator, or for a longer period with the consent of all parties and of the adjudicator.
Read the Federal Prompt Payment for Construction Work Regulations (Dispute Resolution) on the Justice Laws Website ↗
Made under Federal Prompt Payment for Construction Work Act, S.C. 2019, c. 29, s. 387.