Federal Prompt Payment for Construction Work Regulations (Criteria, Time Limits, Interest and Circumstances), SOR/2023-269

Section 3

Days to exclude

Cite as Federal Prompt Payment for Construction Work Regulations (Criteria, Time Limits, Interest and Circumstances), SOR/2023-269, s. 3 · current to July 24, 2025 · regulation last amended December 9, 2023

Statute Watch

Get an alert when a bill in Parliament would change this section, and every time it moves.

The text

The following days and periods are excluded from the computation of time for the purposes of the time limits referred to in sections 9 to 11 of the Act: (a) any holiday as defined in subsection 35(1) of the Interpretation Act; (b) Saturdays; (c) the nine-day period beginning on December 24 and ending on January 1; and (d) any construction holiday that is recognized by any provincial government.
Read the Federal Prompt Payment for Construction Work Regulations (Criteria, Time Limits, Interest and Circumstances) on the Justice Laws Website ↗

Made under Federal Prompt Payment for Construction Work Act, S.C. 2019, c. 29, s. 387.