(1) The holder must maintain a record of all construction of facilities across, on, along or under its international or interprovincial power line and of all activities that cause a ground disturbance within the prescribed area for the life of that line.
(2) The record must contain, for each facility or each activity that causes a ground disturbance,
(a) a copy of the written authorization given by the holder;
(b) in respect of the inspections referred to in paragraphs 5(a) and (b),
(i) the name of the person that conducted the inspection,
(ii) the date and time of the inspection, and
(iii) all findings and observations including any field observations referred to in paragraph 5(c); and
(c) the details of any abandonment, removal or alteration of the facility.
(3) Despite subsection (1), if there is an expiry date set out in the authorization, the holder need only retain the record that contains the copy of the written authorization for a period of 12 months from the day on which the authorization expires.
Read the International and Interprovincial Power Line Damage Prevention Regulations – Obligations of Holders of Permits and Certificates on the Justice Laws Website ↗
Made under Canadian Energy Regulator Act, S.C. 2019, c. 28, s. 10.
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.