International and Interprovincial Power Line Damage Prevention Regulations – Obligations of Holders of Permits and Certificates, SOR/2020-49
Section 4
Time period
Cite as International and Interprovincial Power Line Damage Prevention Regulations – Obligations of Holders of Permits and Certificates, SOR/2020-49, s. 4 · current to July 24, 2025 · regulation last amended September 27, 2022
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
If a holder receives a request to locate the holder’s international or interprovincial power line from a person who intends to construct a facility across, on, along or under an international or interprovincial power line or engage in an activity that causes a ground disturbance within the prescribed area, the holder must, within three working days, after the day on which the request is made, or any longer period agreed to by the holder and that person,
(a) inform the person, in writing, of safety practices to be followed while working in the vicinity of the holder’s international or interprovincial power line and, in case of a ground disturbance, within the prescribed area;
(b) mark the location of the underground portion of the holder’s international or interprovincial power line in the vicinity of the proposed facility or the prescribed area using markings that are clearly visible and distinct from any other markings that may be in the vicinity of the proposed facility or the prescribed area; and
(c) provide information to the person that clearly explains the significance of the markings.
Read the International and Interprovincial Power Line Damage Prevention Regulations – Obligations of Holders of Permits and Certificates on the Justice Laws Website ↗
Made under Canadian Energy Regulator Act, S.C. 2019, c. 28, s. 10.