International and Interprovincial Power Line Damage Prevention Regulations — Authorizations, SOR/2019-347
Section 13
Leave — excavation or construction of facility
Cite as International and Interprovincial Power Line Damage Prevention Regulations — Authorizations, SOR/2019-347, s. 13 · current to July 24, 2025 · regulation last amended March 16, 2020
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
Any excavation or the construction of a facility that was started before the coming-into-force day and for which leave of the National Energy Board was not necessary under paragraph 58.33(c) of the National Energy Board Act, as it read immediately before that day, may be continued after that day if it is carried out in conformity with the applicable conditions set out in section 3 of the Power Line Crossing Regulations, as it read immediately before that day.
Read the International and Interprovincial Power Line Damage Prevention Regulations — Authorizations on the Justice Laws Website ↗
Made under Canadian Energy Regulator Act, S.C. 2019, c. 28, s. 10.
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.