Canadian Energy Regulator Pipeline Damage Prevention Regulations – Obligations of Pipeline Companies, SOR/2016-133
Section 6
Timeline
Cite as Canadian Energy Regulator Pipeline Damage Prevention Regulations – Obligations of Pipeline Companies, SOR/2016-133, s. 6 · current to July 24, 2025 · regulation last amended March 16, 2020
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) Subject to subsection (2), if a pipeline company receives a request to locate its pipes from a person that intends to construct a facility across, on, along or under a pipeline or engage in an activity that would cause a ground disturbance within the prescribed area, the pipeline company must, within three working days after the day on which the request is made, or any longer period agreed to by the pipeline company and that person,
(a) inform the person, in writing, of safety practices to be followed while working in the vicinity of its pipes and, in case of a ground disturbance, within the prescribed area;
(b) mark the location of its pipes in the vicinity of the proposed facility or the prescribed area at maximum intervals of 10 m along each pipe using markings that are clearly visible and distinct from any other markings that may be in the vicinity of the proposed facility or the prescribed area; and
(c) provide information to the person that clearly explains the significance of the markings.
(2) The markings must be consistent with the standards for locating a pipeline that are set out in the pipeline company’s damage prevention program.
Read the Canadian Energy Regulator Pipeline Damage Prevention Regulations – Obligations of Pipeline Companies on the Justice Laws Website ↗
Made under N-7.