Canadian Energy Regulator Pipeline Damage Prevention Regulations – Obligations of Pipeline Companies, SOR/2016-133

Section 4

Information – application for authorization

Cite as Canadian Energy Regulator Pipeline Damage Prevention Regulations – Obligations of Pipeline Companies, SOR/2016-133, s. 4 · current to July 24, 2025 · regulation last amended March 16, 2020

Statute Watch

Get an alert when a bill in Parliament would change this section, and every time it moves.

The text

If a person that intends to construct a facility across, on, along or under a pipeline, engage in an activity that would cause a ground disturbance within the prescribed area of a pipeline or operate a vehicle or mobile equipment across a pipeline has made a request to the pipeline company for the information that is necessary to make an application to the Regulator for authorization, the pipeline company must, within 10 working days after receiving the request, give the person all the information, and provide all reasonable assistance, that is necessary to prepare the application.
Read the Canadian Energy Regulator Pipeline Damage Prevention Regulations – Obligations of Pipeline Companies on the Justice Laws Website ↗

Made under N-7.

Bills in Parliament that would change this section 0