Canadian Energy Regulator Pipeline Damage Prevention Regulations – Authorizations, SOR/2016-124
Section 9
Authorization for construction of overhead line
Cite as Canadian Energy Regulator Pipeline Damage Prevention Regulations – Authorizations, SOR/2016-124, s. 9 · current to July 24, 2025 · regulation last amended March 16, 2020
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) For the purposes of subsection 335(1) of the Act, the construction of an overhead line across a pipeline — in an area other than an offshore area — is authorized if the person that intends to construct the overhead line
(a) makes a locate request in accordance with section 3;
(b) confirms with the pipeline company that all of the pipeline company’s pipes in the vicinity of the construction have been marked; and
(c) obtains from the pipeline company the information that is referred to in paragraphs 6(1)(a) and (c) of the Canadian Energy Regulator Pipeline Damage Prevention Regulations – Obligations of Pipeline Companies.
(2) Any person that is undertaking the construction of an overhead line across a pipeline must comply with the following measures:
(a) construct the overhead line in accordance with any applicable provincial and federal law;
(b) if the pipeline is patrolled by aircraft and if the overhead line poses a risk to the aircraft, install and maintain aerial warning devices; and
(c) not construct or place any kind of pole, pylon, tower, guy, anchor or supporting structure across, on, along or under the pipeline.
Read the Canadian Energy Regulator Pipeline Damage Prevention Regulations – Authorizations on the Justice Laws Website ↗
Made under N-7.
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.