Railway Safety Management System Regulations, 2015, SOR/2015-26
Section 30
Scope and frequency
Cite as Railway Safety Management System Regulations, 2015, SOR/2015-26, s. 30 · current to July 24, 2025 · regulation last amended April 1, 2015
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) A railway company must conduct an audit of its safety management system every three years to evaluate
(a) the extent to which the requirements related to each process have been implemented; and
(b) the extent to which the policy referred to in subsection 24(2) and the procedures, plans and methods developed by the railway company are effective in improving the level of safety of its railway operations.
(2) The railway company must include, in its safety management system, an audit plan that
(a) defines the scope of each audit;
(b) indicates the evaluation criteria to be applied;
(c) specifies the method to be used in conducting each evaluation; and
(d) sets out the schedule for evaluating each process.
Read the Railway Safety Management System Regulations, 2015 on the Justice Laws Website ↗
Made under Railway Safety Act, R.S.C. 1985, c. 32 (4th Supp.).