Passenger Automobile and Light Truck Greenhouse Gas Emission Regulations, SOR/2010-201
Section 30.21
Creation of charging station units
Cite as Passenger Automobile and Light Truck Greenhouse Gas Emission Regulations, SOR/2010-201, s. 30.21 · current to July 24, 2025 · regulation last amended December 15, 2023
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) A company may create charging station units with respect to any registered charging station project if
(a) all charging stations became operational no earlier than on January 1, 2024 and no later than two years after the date of registration of the project, but the date must not be later than December 31, 2027; and
(b) the company reports those units in its end of model year report.
(2) If a company is the only investor in a registered project, the company must calculate the number of charging station units it will create using the following formula:A ÷ BwhereAis the lesser of(a) the total amount of the company’s investment; and(b) the total of the maximum allowable investment amounts for each charging station, in accordance with the table below; andColumn 1Column 2Rated power of charging stationsMaximum investment for each charging station150 kW to 199 kW$150,000200 kW and above$200,000Bis $20,000.
(3) If a company invests in the registered project with other companies or third parties, that company must calculate the number of charging station units it will create using the following formula:(A ÷ B) × CwhereAis the lesser of(a) the total investment amount in the project, and(b) the total of the maximum allowable investment amounts for each charging station, in accordance with the table in subsection (2);Bis $20,000; andCis the proportion of the company’s investment in the project, as compared to the total investment in the project, expressed as a percentage of the total investment.
(4) A company creates charging station units with respect to a registered project on the day on which the end of model year report for the model year in question is submitted.
(5) A company may bank all or some of the charging station units created with respect to the registered project and transfer all or some of them to another company.
(6) The Minister must cancel
(a) in respect of each charging station of the registered project that does not comply with any of subparagraph 30.18(f)(ii) to (vi), those charging station units created with respect to the station; and
(b) in respect of the cancellation of the registration of a project under section 30.20, all units created with respect to that project.
(7) Charging station units are no longer valid after the day on which the company submits its end of model year report for the 2030 model year.
Read the Passenger Automobile and Light Truck Greenhouse Gas Emission Regulations on the Justice Laws Website ↗
Made under Canadian Environmental Protection Act, 1999, S.C. 1999, c. 33.
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.