Northern Pipeline Socio-Economic and Environmental Terms and Conditions for the Province of Saskatchewan, SI/81-23
Section 16
Cite as Northern Pipeline Socio-Economic and Environmental Terms and Conditions for the Province of Saskatchewan, SI/81-23, s. 16 · current to July 24, 2025 · regulation last amended March 22, 2006
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) Foothills shall, within 30 days of the coming into force of this Part or at such later date as may be fixed by the designated officer, submit to the designated officer for his approval a plan schedule that sets out the date each plan referred to in subsection 15(1) is to be submitted to the designated officer.
(2) The plan schedule referred to in subsection (1), when approved by the designated officer, constitutes Foothills’ plan schedule and Foothills shall comply therewith.
(3) The designated officer may, at the request of Foothills, modify or vary the plan schedule referred to in subsection (2).
Read the Northern Pipeline Socio-Economic and Environmental Terms and Conditions for the Province of Saskatchewan on the Justice Laws Website ↗
Made under Northern Pipeline Act, R.S.C. 1985, c. N-26.
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.