The text
Where
(a) Foothills and a claimant against Foothills fail to agree as to liability or compensation for damage for which the claimant alleges Foothills is responsible, and
(b) the claimant referred to in paragraph (a) agrees with Foothills
(i) to enter into an arbitration submission governed by the provisions of the Arbitration Act (British Columbia), and
(ii) that a decision of the arbitrator is binding and conclusive,Foothills shall enter into such arbitration submission and shall pay all costs of and incidental to any arbitration proceedings pursuant thereto except where the arbitrator determines that the claim is frivolous.
Read the Northern Pipeline Socio-Economic and Environmental Terms and Conditions for Northern British Columbia on the Justice Laws Website ↗
Made under Northern Pipeline Act, R.S.C. 1985, c. N-26.