Nunavut Planning and Project Assessment Act, S.C. 2013, c. 14, s. 2
Section 85
Verification — screening
Cite as Nunavut Planning and Project Assessment Act, S.C. 2013, c. 14, s. 2, s. 85 · current to July 24, 2025 · Act last amended May 27, 2022
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) If there is no applicable land use plan, the Commission must, within 45 days after receiving the project proposal, verify whether the project is exempt from screening under subsection 78(2) and must comply with the requirements of section 79 or 80, as the case may be.
(2) The Commission may request the Board’s opinion as to whether a particular project is exempt from screening.
(3) Any time required for the proponent to provide information required under subsection 144(1) does not count as part of the period referred to in subsection (1).
Read the Nunavut Planning and Project Assessment Act on the Justice Laws Website ↗
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.