(1) In conducting a review of a project, a federal environmental assessment panel must take into account the following factors: (a) the purpose of the project, and the need for the project; (b) whether, and to what extent, the project would protect and enhance the existing and future well-being of the residents and communities of the designated area while taking into account the interests of other Canadians; (c) whether the project reflects the priorities and values of the residents of the designated area; (d) the anticipated effects of the environment on the project, including effects associated with natural phenomena, such as meteorological and seismological activity, and climate change; (e) the anticipated ecosystemic and socio-economic impacts of the project, including those arising from the effects referred to in paragraph (d); (f) the cumulative ecosystemic and socio-economic impacts that could result from the impacts of the project combined with those of any other project that has been carried out, is being carried out or is likely to be carried out; (g) whether the impacts referred to in paragraphs (e) and (f) would unduly prejudice the ecosystemic integrity of the designated area; (h) the measures, including those proposed by the proponent, that should be taken to (i) avoid and mitigate adverse ecosystemic and socio-economic impacts, including contingency plans, (ii) optimize the benefits of the project, with specific consideration given to expressed community and regional preferences in regard to benefits, (iii) compensate persons whose interests are adversely affected by the project, and (iv) restore ecosystemic integrity after the permanent closure of the project; (i) the significance of the impacts referred to in paragraphs (e) and (f), taking into account the measures referred to in paragraph (h); (j) the capacity of renewable resources that are likely to be significantly affected by the project to meet the existing and future needs of the residents of the designated area; (k) any monitoring program of the project’s ecosystemic and socio-economic impacts that should be established, including one proposed by the proponent; (l) the interests in land and waters that the proponent has acquired or seeks to acquire; (m) options for carrying out the project that are technically and economically feasible and the anticipated ecosystemic and socio-economic impacts of such options; (n) the posting of performance bonds; (o) the particular issues or concerns identified under sections 97 and 117; (p) the concerns and recommendations referred to in subsection 120(8); and (q) any other matter within its jurisdiction that, in its opinion, should be considered. (2) In determining the significance of impacts for the purposes of paragraph (1)(i), the panel must take into account the factors set out in paragraphs 90(a) to (j). (3) In its review of a project, the panel must take into account any traditional knowledge or community knowledge provided to it.
Read the Nunavut Planning and Project Assessment Act on the Justice Laws Website ↗

Bills in Parliament that would change this section 0

No bill we hold would amend or repeal this section.