Mackenzie Valley Resource Management Act, S.C. 1998, c. 25

Section 72.18

Time limit — type A licence and type B licence

Cite as Mackenzie Valley Resource Management Act, S.C. 1998, c. 25, s. 72.18 · current to July 24, 2025 · Act last amended November 27, 2024

Statute Watch

Get an alert when a bill in Parliament would change this section, and every time it moves.

The text

(1) With respect to a federal area or lands outside a federal area, on an application for the issuance, renewal or amendment of a type A licence, or a type B licence in connection with which a public hearing is held, or if the board intends to consider, on its own initiative, the renewal or amendment of such a licence, the board shall make a decision within a period of nine months after the day on which the application is made or on which notice of the board’s intention is published under subsection 72.17(1) or (2). (2) If the board decides to issue, renew or amend the licence, that decision shall be immediately referred to the federal Minister for approval. (3) The federal Minister shall, within 45 days after the board’s decision is referred to him or her, notify the board whether or not the decision is approved and, if it is not approved, provide written reasons in the notification. (4) The federal Minister may extend the 45-day time limit by not more than an additional 45 days if he or she notifies the board of the extension within the first 45 days. (5) If the federal Minister does not notify the board whether or not the decision is approved within the time limit referred to in subsection (3) or (4), whichever is applicable, the federal Minister is deemed to have given approval.
Read the Mackenzie Valley Resource Management Act on the Justice Laws Website ↗

Bills in Parliament that would change this section 1

  • C-88 An Act to amend the Mackenzie Valley Resource Management Act and the Canada Petroleum Resources Act and to make consequential amendments ... Amends s. 72.18 · 42nd Parliament, 1st session