Impact Assessment Act, S.C. 2019, c. 28, s. 1

Section 37

Time limit

Cite as Impact Assessment Act, S.C. 2019, c. 28, s. 1, s. 37 · current to June 14, 2026 · Act last amended May 29, 2026

Statute Watch

Get an alert when a bill in Parliament would change this section, and every time it moves.

The text

(1) If the Minister refers the impact assessment of a designated project to a review panel, the Agency must establish the following time limits: (a) the time limit, after the day on which the notice referred to in subsection 19(4) with respect to the designated project is posted on the Internet site, within which the review panel must submit a report with respect to that impact assessment to the Minister; and (b) the time limit, after the day on which the review panel submits the report, within which the Agency must post its recommendations under subsection 55.1(2). (2) Subject to subsection (3), the total number of days for the time limits established under subsection (1) must not exceed 600 unless the Agency is of the opinion that more time is required to take into account circumstances that are specific to the designated project or to allow the review panel to cooperate with a jurisdiction referred to in section 21 with respect to the impact assessment of that project. (3) The Minister may extend the time limit established under paragraph (1)(a) by any period — up to a maximum of 90 days — that is necessary to take into account circumstances that are specific to the designated project or to allow the review panel to cooperate with a jurisdiction referred to in section 21. (4) The Governor in Council may, on the recommendation of the Minister, extend the time limit extended under subsection (3) by any period that is necessary to take into account circumstances that are specific to the designated project or to allow the review panel to cooperate with a jurisdiction referred to in section 21. (5) The Agency must post the following items on the Internet site: (a) the Agency’s reasons for establishing the time limits under subsection (1); (b) a notice of any extension granted under subsection (3), including the Minister’s reasons for granting that extension; and (c) a notice of any extension granted under subsection (4), including the Governor in Council’s reasons for granting that extension. (6) The Agency may suspend the time limit within which the review panel must submit the report until any activity that is prescribed by regulations made under paragraph 112(1)(c) is completed. If the Agency suspends the time limit, it must post on the Internet site a notice that sets out its reasons for doing so. (7) When the Agency is of the opinion that the prescribed activity is completed, it must post a notice to that effect on the Internet site.
Read the Impact Assessment Act on the Justice Laws Website ↗

Bills in Parliament that would change this section 2

  • C-39 An Act respecting certain measures to strengthen the economy Amends s. 37 · 45th Parliament, 1st session
  • C-69 An Act to implement certain provisions of the budget tabled in Parliament on April 16, 2024 Amends s. 37 · 44th Parliament, 1st session