Impact Assessment Act, S.C. 2019, c. 28, s. 1
Section 19
Time limit for information or studies
Cite as Impact Assessment Act, S.C. 2019, c. 28, s. 1, s. 19 · current to June 14, 2026 · Act last amended May 29, 2026
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) The proponent of a designated project must provide the Agency with the information or studies that are set out in the notice of the commencement of the impact assessment of the designated project within three years after the day on which a copy of that notice is posted on the Internet site.
(2) On the proponent’s request, the Agency may extend the time limit by any period that is necessary for the proponent to provide the Agency with the information or studies.
(3) If the Agency extends the time limit, it may require the proponent to provide it with any additional information or studies that the Agency considers necessary for it to conduct the impact assessment.
(4) When the Agency is satisfied that the proponent has provided it with all of the information or studies, it must post a notice of that determination on the Internet site.