Dominion Water Power Regulations, C.R.C., c. 1603
Section 7
Cite as Dominion Water Power Regulations, C.R.C., c. 1603, s. 7 · current to July 24, 2025 · regulation last amended August 28, 2019
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) Where the applicant has completed satisfactorily the submission of such of the information required by section 3 and has supplied such of the plans and specifications as will satisfy the Minister that
(a) the proposed development is in general accord with the most beneficial utilization of the stream waters,
(b) the proposed undertaking is feasible and practicable and in the public interest, and
(c) the applicant has the requisite financial ability to carry the project to a successful consummation,the Minister may issue to the applicant a priority permit which shall give the applicant priority over other applicants in the consideration of his general layout plans if filed within the time specified in the permit.
(2) In granting a priority permit the Minister may give preference to an application by a province, municipality or municipal district where he considers such preference to be in the public interest.
(3) No priority permit shall be construed as binding the Minister to issue an interim licence, giving the applicant any exclusive claim or right, or relieving the Minister from considering other possible schemes for the development of the site, if there is reason to believe that they may result in a more beneficial utilization of the natural resources or be otherwise in the public interest.
(4) A priority permit shall be effective for a period not to exceed one year but may be renewed.
(5) No extensions of time to a priority permit shall be granted unless it is shown to the satisfaction of the Minister by statutory declaration by the applicant, and otherwise, that the applicant has promptly and diligently continued the surveys and preparation of the plans in good faith, and has been prevented by causes beyond his control, other than the want of funds, from completing the plans within the time fixed, but the applicant shall not be given an extension of more than one year from the expiry of the time originally fixed.
(6) If the plans and information required are not completed and filed before the expiration of the initial period of the priority permit or of any extension thereof, the applicant’s priority shall lapse.
Read the Dominion Water Power Regulations on the Justice Laws Website ↗
Made under Dominion Water Power Act, R.S.C. 1985, c. W-4.
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.