Dominion Water Power Regulations, C.R.C., c. 1603
Section 29
Cite as Dominion Water Power Regulations, C.R.C., c. 1603, s. 29 · current to July 24, 2025 · regulation last amended August 28, 2019
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
Where it is desired to take over works and lands that are outside the severance line but within the power system, the Minister,
(a) in determining the compensation to be paid for those works,
(i) shall fix a sum that represents their physical value by
(A) considering either first cost, replacement cost or any other similar criteria that will enable him to arrive at the physical value of the works, and
(B) excluding good will, going concern, franchise value, severance damages and any intangible elements of a like nature, and
(ii) may add to the sum representing their physical value an amount not exceeding 10 per cent thereof for the purpose of covering such severance damages as is deemed just;
(b) in determining the compensation to be paid for those lands,
(i) shall take as the basis of such compensation the amount previously established as their actual cost in accordance with section 19,
(ii) shall make an allowance for the variation in the purchasing power of the dollar, and
(iii) may, in his discretion, add to the result so determined a bonus not exceeding 10 per cent thereof to cover such severance and other intangible values as is deemed proper to allow under the circumstances.
Read the Dominion Water Power Regulations on the Justice Laws Website ↗
Made under Dominion Water Power Act, R.S.C. 1985, c. W-4.
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.