Dominion Water Power Regulations, C.R.C., c. 1603
Section 22
Cite as Dominion Water Power Regulations, C.R.C., c. 1603, s. 22 · current to July 24, 2025 · regulation last amended August 28, 2019
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) Where, by reason of engineering difficulties that could not reasonably have been foreseen or by other peculiar or special causes beyond his control other than the want of funds, an interim licensee has been prevented from
(a) filing general construction plans,
(b) commencing construction,
(c) expending sums required to be expended within any stated period, or
(d) completing the initial development,the Minister may grant an extension of time for completing those requirements.
(2) The maximum extension that may be granted for the filing of general construction plans, for the commencement of construction work or for the expenditure of the sums required in an interim licence within the first and second years of the construction period, or within such other stated times as are specified in the interim licence, is 12 months.
Read the Dominion Water Power Regulations on the Justice Laws Website ↗
Made under Dominion Water Power Act, R.S.C. 1985, c. W-4.