Canada Oil and Gas Land Regulations, C.R.C., c. 1518
Section 51
Cite as Canada Oil and Gas Land Regulations, C.R.C., c. 1518, s. 51 · current to July 24, 2025 · regulation last amended March 22, 2006
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) Every licensee, permittee or lessee shall, at least 15 days prior to commencing exploratory work, send a written notice, in duplicate, in a form approved by the Chief, to the Oil Conservation Engineer stating
(a) the date on which he expects to commence the work and to complete the work;
(b) the purpose and nature of the work;
(c) the approximate acreage of the area on which the work is to be done together with a map showing the boundaries of the area;
(d) the equipment he intends to use;
(e) the name of the person in charge of the work; and
(f) the number of persons to be employed.
(2) Notwithstanding subsection (1), every licensee, permittee or lessee shall send the written notice, as required by that subsection, at least 45 days prior to commencing exploratory work on an area that is wholly or partially covered by seacoast waters.
Read the Canada Oil and Gas Land Regulations on the Justice Laws Website ↗
Made under Territorial Lands Act, R.S.C. 1985, c. T-7; Federal Real Property and Federal Immovables Act, S.C. 1991, c. 50.
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.