Hull Construction Regulations, C.R.C., c. 1431

Section 28

Cite as Hull Construction Regulations, C.R.C., c. 1431, s. 28 · current to July 24, 2025 · regulation last amended December 20, 2023

Statute Watch

Get an alert when a bill in Parliament would change this section, and every time it moves.

The text

(1) If watertight bulkheads are recessed, the recess shall be inboard from the ship’s side by at least one-fifth the beam amidships measured at right angles to the centre line at the level of the load water line; otherwise, the bulkhead shall comply with the requirements for a stepped bulkhead. (2) In the case of ships that operate solely on the Great Lakes, where the maximum moulded beam at the deck and at the load water line differ appreciably, the inboard damage penetration may be assumed at a mean position between that corresponding to one-fifth of the maximum moulded beam at the deck, measured inboard at the deck, and that corresponding to one-fifth the maximum moulded beam at the load water line measured inboard at the load water line.
Read the Hull Construction Regulations on the Justice Laws Website ↗

Made under Canada Shipping Act, 2001, S.C. 2001, c. 26.

Bills in Parliament that would change this section 0

No bill we hold would amend or repeal this section.