Canadian Energy Regulator Act, S.C. 2019, c. 28, s. 10
Section 232
Interim tolls
Cite as Canadian Energy Regulator Act, S.C. 2019, c. 28, s. 10, s. 232 · current to March 31, 2026 · Act last amended March 26, 2026
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
If the Commission has made an interim order authorizing a company to charge tolls until a specified time or the happening of a specified event, the Commission may, in any subsequent order, direct the company
(a) to refund, in the manner that the Commission considers appropriate, the part of the tolls charged under the interim order that is in excess of the tolls determined by the Commission to be just and reasonable, together with interest on the amount to be refunded; or
(b) to recover in its tolls, in the manner that the Commission considers appropriate, the amount by which the tolls determined by the Commission to be just and reasonable exceed the tolls charged under the interim order, together with interest on the amount to be recovered.