An Act amending Title 66 (Public Utilities) of the Pennsylvania Consolidated Statutes, in restructuring of ...
This bill amends Pennsylvania's Municipalities Planning Code to establish definitions and provisions concerning renewable energy facilities. It includes regulations for solar and wind energy facilities, energy storage, and comprehensive plans for energy use.
Do you support it?
Want to know if it passes?
We'll email you when HB 2880 moves — a committee vote, a floor vote, or a signature. Nothing else.
Free forever · unsubscribe in one click.
Your answer was recorded either way.
Which district are you in?
Your ZIP is all we need to match you to your own representatives — so we can tell you how they voted on HB 2880.
You're tracking HB 2880
We'll email you the moment it moves.
HB 2880 — An Act amending Title 66 (Public Utilities) of the Pennsylvania Consolidated Statutes, in restructuring of electric utility industry, further providing for definitions and for duties of electric distribution companies.
Last action — Corrective Reprint, Printer's No. 4100, Oct. 27, 2026
No card. One bill, free forever — alerts when it moves.
-
✓Introduced
-
2In Committee
-
3Passed House
-
4Passed Senate
-
5To Executive
-
6Enacted
This bill is in committee in the House. Introduced October 21, 2026. It must pass committee before a floor vote.
Next likely step: a committee vote, then a floor vote in the House.
Prognosis
Where this bill stands today.
Odds of enactment
LowHow often bills like it became law.
-
In Committee
Current position in the legislative process.
-
6 sponsors
1 primary, 5 co-sponsors signed on.
-
Bipartisan support
Sponsored across 2 parties (4 D · 1 R) — cross-party backing.
Prognosis reads this bill's own signals — stage, sponsorship breadth, committee status, recorded votes and cross-state momentum. Odds come from a model trained on which bills have become law.
In plain language
The bill updates planning codes to include renewable energy standards and definitions in Pennsylvania.
This bill amends Pennsylvania's Municipalities Planning Code to establish definitions and provisions concerning renewable energy facilities. It includes regulations for solar and wind energy facilities, energy storage, and comprehensive plans for energy use.
What this means for you
- Environment: This bill promotes the development and integration of renewable energy facilities, supporting environmental sustainability efforts.
Summary
Cutting Costs and Expanding Access to Customer-Owned Energy
Bill Text
What changed in the latest version
111 added · 542 removedPlain-language change summary
The amendment adds definitions for "Generator disconnect switch" and "Meter socket adapter" to Section 2803 of Title 66 of the Pennsylvania Consolidated Statutes. These definitions clarify the purpose and safety standards related to devices that isolate distributed energy resources and facilitate the installation of electric meters. This addition helps establish a clearer understanding of components related to the electric distribution system, which may affect how electric distribution companies manage and implement energy resources.
CORRECTIVE REPRINT PRIOR PRINTER'S NO.
4096 THEPRINTER'S GENERALNO. ASSEMBLY OF PENNSYLVANIA HOUSE BILL Session of No.
28804100 2026THE INTHOHENSTEIN,GENERAL OCTOBERASSEMBLY 21,OF 2026GH,PENNSYLVANIA GUZMAN,HOUSE PIELLIBILL ANDSession REFERRED TO COMMITTEE ON CONSUMER PROTECTION, TECHNOLOGY AND UTILITIES, OCTOBER 21, 2026 AN ACT Amending the act of JulyNo. 31, 1968 (P.L.805, No.247), entitled "An act to empower cities of the second class A, and third class, boroughs, incorporated towns, townships of the first second class and counties of the second through eighththe classes, individually or jointly, to plan their development and to govern the same by zoning, subdivision and land development ordinances, planned residential development and other ordinances, by official maps, by the reservation of certain land for future public purpose and by the acquisition of such land;
to2880 promote2026 theINTAND conservationRIVERA, ofOCTOBER energy21, through2026GH, GUZMAN, PIELLI, HOHENSTEIN REFERRED TO COMMITTEE ON CONSUMER PROTECTION, TECHNOLOGY AND UTILITIES, OCTOBER 21, 2026 AN ACT Amending Title 66 (Public Utilities) of the usePennsylvania ◄ Consolidated Statutes, in restructuring of planningelectric practicesutility and◄ toindustry, promotefurther theproviding effectivefor utilizationdefinitions and for duties of renewable◄ energyelectric sources;distribution companies.
providing◄ forThe theGeneral establishmentAssembly of planningthe commissions,Commonwealth planningof departments,Pennsylvania planning◄ committeeshereby andenacts zoningas hearingfollows: boards, authorizing them to charge fees, make inspections and hold public hearings;
providing◄ forSection mediation;1.
providingSection for2803 transferableof developmentTitle rights;66 of the Pennsylvania ◄ Consolidated Statutes is amended by adding definitions to read:
providing◄ for§ appropriations,2803. appeals to courts and penalties for violations;
and repealing acts and definitions;
in comprehensive plan, further providing forfor preparation of comprehensive plan;
in subdivision and land development, further providing for contents of subdivision and land development ordinance;
in zoning, further providing for ordinance provisions;
and providing for renewable energy siting standards.
The General Assembly of the Commonwealth of Pennsylvania hereby enacts as follows:
Section 1.
Section 107(a) of the act of July 31, 1968 (P.L.805, No.247), known as the Pennsylvania Municipalities Planning Code, is amended by adding definitions to read:
Section 107.
Definitions.--(a) The following words and phrases when used in this act shall have the meanings given to them in this subsection unless the context clearly indicates otherwise:
* * * "Combined energy generation and storage facility," a solar energy facility or wind energy facility that is paired with an energy storage facility and has a maximum facility output of at least 20 megawatts and the technical capacity to deliver the maximum facility output for a minimum duration of at least four hours.
* * * "Energy storage facility," a facility located in this Commonwealth that employs technology, including electrochemical, thermal or electromechanical technology or a technology defined as "energy storage technology" in 26 U.S.C.
§ 48E (relating to clean energy investment credit) or 26 CFR 1.48E-2(g)(6) (relating to qualified investments in qualified facilities and EST for purposes of section 48E) on the effective date of this definition, that is capable of absorbing and storing energy for use at a later time, is designed primarily to store energy for, and is connected to, the wholesale or distribution grid and has a maximum facility output of at least five megawatts and the technical capacity to deliver the maximum facility output for a minimum duration of at least four hours.
* * * "Renewable energy facility," a solar energy facility, wind energy facility, energy storage facility or combined energy 20260HB2880PN4096 - 2 - generation and storage facility.
* * * "Solar energy facility," a system that captures and converts solar energy into electricity for sale or for use in locations other than solely on the property of the solar energy facility, is connected to the wholesale or distribution grid and has a nameplate capacity of at least 20 megawatts.
* * * "Wind energy facility," a system that captures and converts wind into electricity for sale or for use in locations other than solely on the property of the wind energy facility, is connected to the wholesale or distribution grid and has a nameplate capacity of at least 20 megawatts.
* * * Section 2.
Section 301(a)(6)(viii) and (ix) of the act are amended and the paragraph is amended by adding a subparagraph to read:
Section 301.
Preparation of Comprehensive Plan--(a) The municipal, multimunicipal or county comprehensive plan, consisting of maps, charts and textual matter, shall include, but need not be limited to, the following related basic elements:
* * * (6) A plan for the protection of natural and historic resources to the extent not preempted by Federal or State law.
This clause includes, but is not limited to, wetlands and aquifer recharge zones, woodlands, steep slopes, prime agricultural land, flood plains, unique natural areas and historic sites.
The plan shall be consistent with and may not exceed those requirements imposed under the following:
20260HB2880PN4096 - 3 - * * * (viii) act of June 10, 1982 (P.L.454, No.133), entitled "An act protecting agricultural operations from nuisance suits and ordinances under certain circumstances";
[and] (ix) act of May 20, 1993 (P.L.12, No.6), known as the "Nutrient Management Act," regardless of whether any agricultural operation within the area to be affected by the plan is a concentrated animal operation as defined under the act[.];
and (x) Article VI-A.
* * * Section 3.
Section 503(1) introductory paragraph of the act is amended to read:
Section 503.
Contents of Subdivision and Land Development Ordinance.--The subdivision and land development ordinance may include, but need not be limited to:
(1) Provisions for the submittal and processing of plats, including the charging of review fees, and specifications for such plats, including certification as to the accuracy of plats and provisions for preliminary and final approval and for processing of final approval by stages or sections of development.
Review fees for the development and construction of a renewable energy facility shall be subject to section 606-A.
Show all 180 changed lines (140 more)
Such plats and surveys shall be prepared in accordance with the act of May 23, 1945 (P.L.913, No.367), known as the "Engineer, Land Surveyor and Geologist Registration Law," except that this requirement shall not preclude the preparation of a plat in accordance with the act of January 24, 1966 (1965 P.L.1527, No.535), known as the 20260HB2880PN4096 - 4 - "Landscape Architects' Registration Law," when it is appropriate to prepare the plat using professional services as set forth in the definition of the "practice of landscape architecture" under section 2 of that act.
Review fees may include reasonable and necessary charges by the municipality's professional consultants for review and report thereon to the municipality.
Such review fees shall be based upon a schedule established by ordinance or resolution.
Such review fees shall be reasonable and in accordance with the ordinary and customary charges for similar service in the community, but in no event shall the fees exceed the rate or cost charged by the professional consultant for comparable services to the municipality for services which are not reimbursed or otherwise imposed on applicants.
Fees charged to the municipality relating to any appeal of a decision on an application shall not be considered review fees and may not be charged to an applicant.
* * * Section 4.
Section 603(b) introductory paragraph of the act is amended and the section is amended by adding a subsection to read:
Section 603.
Ordinance Provisions.--* * * (b) Zoning ordinances, except to the extent that those regulations of mineral extraction by local ordinances and enactments have heretofore been superseded and preempted by the act of May 31, 1945 (P.L.1198, No.418), known as the "Surface Mining Conservation and Reclamation Act," the act of December 19, 1984 (P.L.1093, No.219), known as the "Noncoal Surface Mining Conservation and Reclamation Act," and the act of December 19, 1984 (P.L.1140, No.223), known as the "Oil and Gas 20260HB2880PN4096 - 5 - Act," and to the extent that the subsidence impacts of coal extraction are regulated by the act of April 27, 1966 (1st Sp.Sess., P.L.31, No.1), known as "The Bituminous Mine Subsidence and Land Conservation Act," and that regulation of activities related to commercial agricultural production would exceed the requirements imposed under the act of May 20, 1993 (P.L.12, No.6), known as the "Nutrient Management Act," regardless of whether any agricultural operation within the area to be affected by the ordinance would be a concentrated animal operation as defined by the "Nutrient Management Act," the act of June 30, 1981 (P.L.128, No.43), known as the "Agricultural Area Security Law," or the act of June 10, 1982 (P.L.454, No.133), entitled "An act protecting agricultural operations from nuisance suits and ordinances under certain circumstances," and that regulation of activities related to the siting of a renewable energy facility would exceed the requirements imposed under Article VI-A, or that regulation of other activities are preempted by other Federal or State laws, may permit, prohibit, regulate, restrict and determine:
* * * (m) Zoning ordinances shall provide for the development and construction of renewable energy facilities in each municipality in a manner consistent with Article VI-A.
Section 5.
The act is amended by adding an article to read:
ARTICLE VI-A RENEWABLE ENERGY SITING STANDARDS Section 601-A.
◄ The following words and phrases when used in this articlechapter ◄ shall have the meanings given to them in this section unless the ◄ context clearly indicates otherwise:
20260HB2880PN4096◄ -* 6* -* "Cumulative◄ environmental"Generator impact."disconnect Theswitch." existingA anddevice reasonablyinstalled foreseeablefor environmentalthe and◄ publicpurpose healthof impactisolating ofdistributed pollutionenergy inresources afrom definedthe geographic◄ areaelectric resultingdistribution fromsystem, pollutioncapable of land,being wateropened orand ambientlocked air,◄ includingin athe reasonablyopen foreseeableposition upstreamand ormeeting downstreamthe impact,requirements regardless of whetherthe ◄ National Electric Code, the pollutionNational hasElectrical beenSafety authorizedCode underor the◄ lawsother ofapplicable thisnationally Commonwealth.recognized safety standards.
"Unauthorized◄ local"Meter ordinance."socket adapter." An ordinanceelectronic adopteddevice orthat enforcedis by◄ installed between a municipalityresidential thatelectric prohibitsmeter orand unreasonablythe delays,meter impedes◄ orsocket preventsfor the construction,purpose operationof orfacilitating maintenancethe deployment of a◄ renewablecustomer-owned or customer-leased technology, including, but not ◄ limited to, interconnection for solar installations, isolation ◄ of battery energy facility,storage unlesssystems theand ordinanceload ismanagement necessaryfor to◄ protectelectric publicvehicle health,chargers safetyand orother welfare.new loads.
◄ * * * ◄ Section 602-A.2.
OrdinanceSection compliance.2807 of Title 66 is amended by adding a ◄ subsection to read:
(a)◄ Amendment.--A§ municipality2807. that has adopted a subdivision and land development ordinance or zoning ordinance that is inconsistent with this article shall amend the ordinance to comply with this article within six months of the effective date of this subsection.
(b)Duties Effect of inconsistency.--Afterelectric thedistribution expirationcompanies. of the period under subsection (a), a provision of a subdivision and land development ordinance or zoning ordinance that is inconsistent with this article shall be unenforceable to the extent of the inconsistency.
(c)◄ Remedies.--A* failure* to* comply◄ with(f.1) thisMeter sectionsocket mayadapter beauthorization.-- addressed◄ under(1) sectionAn 608-Aelectric distribution company shall authorize the ◄ installation and operation of a meter socket adapter, whether ◄ owned by a residential customer or anyby othera applicablethird provisionparty, if the ◄ meter socket adapter meets all of thisthe act.following criteria:
Section◄ 603-A.(i) The meter socket adapter is qualified to be ◄ connected to the supply side of the service disconnect in ◄ conformity with the applicable provisions of the National ◄ Electric Code.
Regulation◄ of(ii) renewableThe energymeter facilities.socket adapter is approved or listed ◄ by a nationally recognized testing laboratory and rated ◄ appropriately for the meter socket for which it is ◄ intended to be installed.
(a)◄ Existing(iii) approvalThe procedure.--Ameter municipalitysocket thatadapter permitsis acertified renewableto energymeet facility◄ throughall aapplicable specialstandards, exceptionas ordetermined conditionalby usea onnationally the◄ effectiverecognized datetesting oflaboratory. this subsection 20260HB2880PN4096 - 7 - shall comply with the procedures and requirements under this article.
(b)◄ Permitted(iv) zoningThe districts.--Ameter municipalitysocket shalladapter permitdoes thenot developmentimpede andaccess construction◄ of20260HB2880PN4100 a- renewable2 energy- facilityto bythe right,sealed specialmeter exceptionsocket compartment or conditionalthe usepull in◄ ansection areaof zonedthe forservice agriculturalsection of the electric meter or industrial◄ use.switchboard, as applicable.
(c)◄ Restriction.--A(2) municipalityA maymanufacturer notof adopta meter socket adapter, a permitthird requirement◄ party, a residential customer or zoningan ordinanceelectric fordistribution the◄ developmentcompany andmay constructioninstall, ofmaintain or service a renewablemeter energysocket facility◄ adapter or associated equipment, provided that isonly morequalified restrictive◄ thanpersonnel themay requirementsphysically underaccess thisthe article.meter socket.
(d)For Technical◄ assistance.--Thepurposes Centerof forthis Localsubsection, Governmentthe Servicesterm may"qualified providepersonnel" technical◄ assistancemeans toan aindividual municipalitywho tois assistproperly trained and authorized ◄ under applicable regulations of the municipalitycommission inand adoptingwho ormeets amending◄ anall ordinancequalifications necessary to complysafely withaccess theelectric procedures◄ metering equipment under thisthe article.National Electrical Safety Code ◄ or other nationally recognized safety standards.
Section◄ 604-A.(3) Immediately after the effective date of this ◄ paragraph, an electric distribution company shall modify the ◄ company's electric service requirements as necessary to ◄ implement this subsection.
Public◄ participation.(4) An electric distribution company shall establish and ◄ publish a point of contact to which device manufacturers may ◄ submit formal requests for approval of meter socket adapters.
(a)◄ Consultation.--Prior(5) toAn filingelectric andistribution applicationcompany forshall development,approve anor applicant◄ disapprove a meter socket adapter for installation within the development◄ ofcompany's aservice renewableterritory energyno facilitylater shallthan consult60 withdays theafter governinga body◄ ofmanufacturer eachor municipalitythird inparty whichsubmits thea renewablerequest energyfor facilityapproval isof proposed◄ toa bespecific located.model of the meter socket adapter.
(b)◄ Contents(6) ofAn consultation.--Consultationelectric underdistribution subsectioncompany (a) shall includeprovide good◄ faithpublic effortsnotice toof meetall withdecisions theapproving governingor bodydisapproving ora the◄ governingmeter body'ssocket designeeadapter toby discussposting the proposedinformation renewableon energythe facility.◄ company's publicly accessible Internet website.
TheIf discussionan ◄ 20260HB2880PN4100 - 3 - electric distribution company disapproves a meter socket ◄ adapter, the company shall includeprovide alla clear and detailed ◄ explanation to the requesting manufacturer or third party on ◄ the reasons for the disapproval within 15 days of the following:◄ disapproval.
(1)◄ Why(7) An approved model of meter socket adapter that ◄ contains a generator disconnect switch in compliance with the site◄ wasNational selected.Electric Code shall be permitted to meet the ◄ requirement for a readily accessible disconnect switch for ◄ distributed energy resources installed at a single-phase ◄ electric service location utilizing a self-contained company ◄ meter.
(2)◄ Alternative(8) locationsWhen thata distributed energy resource installation ◄ utilizes a meter socket adapter equipped with an internal ◄ disconnect switch, the applicantelectric considered.distribution company may not ◄ require any further or additional disconnect switches.
(3)An Viewshed◄ impacts.installation utilizing a disconnect switch contained in a ◄ meter socket adapter shall comply with all applicable ◄ electric distribution company and local requirements for ◄ labeling, as applicable.
(4)◄ Environmental* impacts.* * ◄ Section 3.
(5) How the applicant plans to mitigate the impacts 20260HB2880PN4096 - 8 - under paragraphs (3) and (4).
(6) Potential benefits to the community.
(c) Community benefit agreement.--An applicant for the development of a renewable energy facility shall enter into a community benefit agreement with the governing body of each municipality in which the renewable energy facility is proposed to be located.
The following requirements and procedures shall apply to a community benefit agreement:
(1) The community benefit agreement shall require that, upon commencement of operation, the owner or operator of the renewable energy facility pay each affected municipality $1,000 total per megawatt of nameplate capacity located within the affected municipality.
If a renewable energy facility is located in more than one municipality, the payment under this paragraph shall be prorated among the affected municipalities based on the portion of the project area located in each municipality.
The affected governing body shall use the payment for police, fire, public safety or other infrastructure or for another project agreed to by the governing body and the applicant.
(2) If an affected governing body refuses to enter into a community benefit agreement after good faith negotiations with the applicant, the applicant shall enter into a community benefit agreement with one or more community-based organizations within the municipality or serving residents of the municipality.
The amount paid by the applicant under this paragraph must be at least equal to the amount that the applicant would pay to the affected municipality under paragraph (1).
(3) A community benefit agreement shall prioritize 20260HB2880PN4096 - 9 - benefits to the municipality in which the renewable energy facility is proposed to be located.
The topics and specific terms of a community benefit agreement may vary and may include any of the following:
(i) Workforce development, job quality and job access provisions.
(ii) Funding for, or providing, specific environmental benefits.
(iii) Funding for, or providing, specific community improvements or amenities, including park and playground equipment, urban greening, enhanced safety crossings, road paving and bike paths.
(iv) Annual contributions to a nonprofit or community-based organization that awards grants.
(4) A community benefit agreement is legally binding and inures to the benefit of the parties and their successors.
The governing body shall enforce the requirement to enter into a community benefit agreement.
A party to a community benefit agreement may enforce the community benefit agreement in a court of competent jurisdiction.
(5) A community benefit agreement under this subsection may not bind the owner or operator of a renewable energy facility if the owner or operator withdraws the application for development or the renewable energy facility is not placed into service.
(d) Technical reports.--At the time of the consultation under subsection (a), the applicant shall provide the governing body with a copy of each technical report concerning the need for the renewable energy facility.
The information provided under this subsection shall include all of the following:
20260HB2880PN4096 - 10 - (1) A map indicating the area of need.
(2) The location of existing surrounding facilities.
(3) A detailed description of the proposed site under consideration.
(4) A description of the site selection process undertaken by the prospective applicant.
(5) The potential environmental impacts of the proposed renewable energy facility.
(6) How the proposed renewable energy facility's potential impacts could affect cumulative environmental impacts in the municipality in which the facility is proposed to be located.
(7) How the applicant plans to mitigate cumulative environmental impacts.
Section 605-A.
Siting standards for renewable energy facilities.
(a) Maximum standards.--A zoning ordinance may include provisions regulating setback distances and heights of renewable energy facilities if the provisions do not exceed the following standards:
(1) A solar energy facility shall comply with the following:
(i) Setback distances must be measured from the nearest edge of an above-ground component of the facility, not including fencing.
(ii) A setback distance of 50 feet from the lot lines of other unoccupied real property, electric substations and railroad, overhead utility line or transit rights-of-way.
(iii) A setback distance of 150 feet from an 20260HB2880PN4096 - 11 - existing school, public playground, public park, child- care facility, church, meetinghouse or other actual place of regularly stated religious worship.
(iv) A municipality may require vegetative screening, including plantings of less than five feet in height.
When a municipality proposes to adopt screening requirements, the municipality shall consider the size and location of the facility, visibility from residential buildings, compatibility of native plant species, cost and feasibility of installation and maintenance and industry standards and best practices for solar energy facilities.
(v) The height of a solar panel may not exceed 25 feet above ground when the solar energy facility's arrays are at full tilt.
(vi) A municipality may require the owner or operator of the solar energy facility to maintain ground cover and topsoil at the site.
(vii) A municipality shall require an applicant for the development of a solar energy facility to submit a decommissioning plan and proof of financial assurance.
The applicant shall retain a third party with expertise in decommissioning to calculate the estimated cost to decommission the solar energy facility.
The financial assurance shall be in an amount that is not less than the estimated cost to decommission the solar energy facility, after deducting salvage or recycling value.
(2) An energy storage facility shall comply with the following:
(i) Setback distances must be measured from the 20260HB2880PN4096 - 12 - nearest edge of the nearest battery or other electrochemical or electromechanical enclosure.
(ii) A setback distance of 150 feet from a residential dwelling or existing school, public playground, public park, child-care facility, church, meetinghouse or other actual place of regularly stated religious worship.
(iii) A setback distance of 50 feet from the lot lines of other unoccupied real property, electric substations and railroad, overhead utility line or transit rights-of-way.
(iv) A municipality may require vegetative screening, including plantings of less than five feet in height.
(v) A municipality may require the energy storage facility to comply with National Fire Protection Association 855, Standard for the Installation of Stationary Energy Storage Systems as in effect on the effective date of this subparagraph.
(vi) The perimeter of an energy storage facility must be enclosed by fencing of a height not greater than 25 feet.
(vii) A municipality shall require an applicant for the development of an energy storage facility to submit a decommissioning plan and emergency response plan.
(3) A wind energy facility shall comply with the following:
(i) Setback distances must be measured from the center of the base of the wind tower.
(ii) A setback distance of 2.1 times the maximum 20260HB2880PN4096 - 13 - blade tip height of the wind tower from a residential dwelling, existing school, public playground, public park, child-care facility, church, meetinghouse or other actual place of regularly stated religious worship or the lot line of an environmentally sensitive area or area of historic significance.
(iii) A setback distance of 1.1 times the maximum blade tip height of the wind tower from the lot lines of other unoccupied real property, electric substations and railroad, overhead utility line or transit rights-of-way.
(iv) A municipality may require limits on the blade tip height of a wind tower located at a wind energy facility if the requirements are not more restrictive than the height permitted under a Determination of No Hazard to Air Navigation issued by the Federal Aviation Administration under 14 CFR Pt.
77 (relating to safe, efficient use, and preservation of the navigable airspace).
(v) The wind energy facility shall be sited so that industry-standard computer modeling indicates that a residential dwelling, existing school, public playground, public park, child-care facility, church, meetinghouse or other actual place of regularly stated religious worship will not experience more than 30 hours per year of shadow flicker under planned operations.
(4) A renewable energy facility may not exceed 47 decibels measured within 30 feet of a residential dwelling, existing school, public playground, public park, child-care facility, church, meetinghouse or other actual place of regularly stated religious worship.
After commercial 20260HB2880PN4096 - 14 - operation, a municipality may require the owner or operator of a renewable energy facility to provide octave band sound pressure level measurements from a reasonable number of sampled locations at the perimeter of the renewable energy facility to demonstrate compliance with this paragraph.
(b) Environmentally sensitive and historic areas.--A municipality may require a renewable energy facility to have an additional setback distance of 50 feet from an environmentally sensitive area or area of historic significance.
(c) Waiver.--A municipality may waive a requirement under this section if each affected property owner provides written consent.
(d) Negotiated setback distances.--Nothing in this section shall be construed to prohibit a municipality and an applicant from negotiating larger setback distances based on the specific needs of the proposed development.
(e) Other law.--Nothing in this section shall be construed to exempt a renewable energy facility from the requirements of the National Electrical Code, National Electrical Safety Code, 34 Pa.
Code Ch.
403 (relating to administration), 52 Pa.
Code § 57.28 (relating to electric safety standards), the act of November 10, 1999 (P.L.491, No.45), known as the Pennsylvania Construction Code Act or another applicable Federal or State law.
Section 606-A.
Permit and application fees.
(a) Reasonableness.--A municipality's application filing fees, review fees and impact fees for the development and construction of a renewable energy facility shall be reasonable and processed in accordance with a fee schedule or invoice.
(b) Limitation.--Fees charged by a municipality for the 20260HB2880PN4096 - 15 - development of a renewable energy facility may not exceed the lesser of:
(1) $1,000 per megawatt of nameplate capacity of the renewable energy facility;
or (2) $100,000.
(c) Reimbursement.--A municipality may require the applicant to reimburse the municipality for reasonable expenses incurred in processing an application that exceed $100,000.
(d) Construction deadline.--Upon approval of an application for development, a municipality may not impose a deadline of less than five years to begin the construction or development of a renewable energy facility.
A municipality shall permit an applicant to request an extension of the deadline for good cause shown.
Section 607-A.
Attorney General review.
(a) Request.--A person aggrieved by the enactment or enforcement of a local ordinance that the person believes to be an unauthorized local ordinance may request that the Attorney General review the local ordinance and consider whether to bring an action under section 608-A.
(b) Discretion.--The Attorney General shall have complete discretion to determine whether to bring an action under section 608-A.
(c) Response.--Within 120 days of receiving a request under subsection (a), the Attorney General shall advise the aggrieved person in writing whether the Attorney General will bring an action against the municipality.
Section 608-A.
Right of action.
(a) Attorney General.--Notwithstanding Article X-A, the Attorney General may bring an action against a municipality in 20260HB2880PN4096 - 16 - Commonwealth Court to invalidate an unauthorized local ordinance or enjoin the enforcement of an unauthorized local ordinance.
(b) Aggrieved person.--Notwithstanding Article X-A or 42 Pa.C.S.
Ch.
85 Subch.
C (relating to actions against local parties), a person aggrieved by the enactment or enforcement of an unauthorized local ordinance may bring an action against a municipality in Commonwealth Court to invalidate the unauthorized local ordinance or enjoin the enforcement of the unauthorized local ordinance.
(c) Remedies.--In an action brought under subsection (b), the court may take any of the following actions:
(1) If the court determines that the municipality enacted or enforced an unauthorized local ordinance with negligent disregard of the limitation of authority established under State law, order the municipality to pay the plaintiff reasonable attorney fees and other litigation costs incurred by the plaintiff in connection with the action.
(2) If the court determines that the action brought by the plaintiff was frivolous or brought without substantial justification in claiming that the local ordinance was unauthorized, order the plaintiff to pay the municipality reasonable attorney fees and other litigation costs incurred by the municipality in defending the action.
(d) Report.--The Attorney General shall provide an annual report to the chairperson and minority chairperson of the Environmental Resources and Energy Committee of the Senate and the chairperson and minority chairperson of the Energy Committee of the House of Representatives.
The report must include all of the following:
20260HB2880PN4096 - 17 - (1) The number of reviews requested, the nature of the complaints and the location of the ordinances cited.
(2) The number of reviews conducted.
(3) The number of legal actions brought by the Attorney General under subsection (a).
(4) The outcome of legal actions brought by the Attorney General under subsection (a).
Section 609-A.
Certain actions prohibited.
A municipality may not adopt or enforce an unauthorized local ordinance.
Section 610-A.
Applicability.
Sections 607-A and 608-A shall apply to the enforcement of local ordinances existing on the effective date of this section and the enactment or enforcement of local ordinances on or after the effective date of this section.
Section 6.
20260HB2880PN4096◄ 20260HB2880PN4100 - 184 -
Show all 180 changed rows (140 more)
AI-generated reading aid from the bill's amendatory text — verify against the official bill.
The bill establishes new definitions and standards for renewable energy facilities, amending the existing municipal planning code to incorporate provisions for their development and siting.
-
Section 107(a)
"Combined energy generation and storage facility," a solar energy facility or wind energy facility that is paired with an energy storage facility and has a maximum facility output of at least 20 megawatts and the technical capacity to deliver the maximum facility output for a minimum duration of at least four hours.
Adds a new definition for combined energy generation and storage facilities.
-
Section 107(a)
"Energy storage facility," a facility located in this Commonwealth that employs technology, including electrochemical, thermal or electromechanical technology or a technology defined as "energy storage technology" in 26 U.S.C. § 48E (relating to clean energy investment credit) or 26 CFR 1.48E-2(g)(6) (relating to qualified investments in qualified facilities and EST for purposes of section 48E) on the effective date of this definition, that is capable of absorbing and storing energy for use at a later time, is designed primarily to store energy for, and is connected to, the wholesale or distribution grid and has a maximum facility output of at least five megawatts and the technical capacity to deliver the maximum facility output for a minimum duration of at least four hours.
Introduces a definition for energy storage facilities.
-
Section 107(a)
"Renewable energy facility," a solar energy facility, wind energy facility, energy storage facility or combined energy generation and storage facility.
Defines renewable energy facilities to include various types of energy generation and storage.
-
Section 301(a)(6)(viii) and (ix)
[and]→ [and] (x) Article VI-A.Adds a reference to Article VI-A related to renewable energy siting standards in the comprehensive planning requirements.
-
Section 503(1)
Review fees for the development and construction of a renewable energy facility shall be subject to section 606-A.
Specifies that review fees for renewable energy facilities will adhere to a specific section.
-
Section 603(b)
that regulation of activities related to the siting of a renewable energy facility would exceed the requirements imposed under Article VI-A,→ that regulation of activities related to the siting of a renewable energy facility would exceed the requirements imposed under Article VI-A,Clarifies that zoning ordinances must comply with Article VI-A regarding renewable energy facilities.
-
Article VI-A
ARTICLE VI-A RENEWABLE ENERGY SITING STANDARDS
Creates a new article establishing siting standards for renewable energy.
-
Section 601-A
"Unauthorized local ordinance." An ordinance adopted or enforced by a municipality that prohibits or unreasonably delays, impedes or prevents the construction, operation or maintenance of a renewable energy facility, unless the ordinance is necessary to protect public health, safety or welfare.
Defines unauthorized local ordinances that hinder the development of renewable energy facilities.
-
Section 602-A
Amendment.--A municipality that has adopted a subdivision and land development ordinance or zoning ordinance that is inconsistent with this article shall amend the ordinance to comply with this article within six months of the effective date of this subsection.
Requires municipalities to amend inconsistent subdivision and zoning ordinances within six months.
-
Section 603-A
Regulation of renewable energy facilities.
Establishes new regulations for the permitting of renewable energy facilities.
Action History
-
Corrective Reprint, Printer's No. 4100, Oct. 27, 2026
-
Referred to CONSUMER PROTECTION, TECHNOLOGY AND UTILITIES, Oct. 21, 2026
Sponsors
- RIVERA · Cosponsor
- Nathan Davidson · Primary
- Perry A. Stambaugh · Cosponsor
- Manuel Guzman · Cosponsor
- Chris Pielli · Cosponsor
- Joseph C. Hohenstein · Cosponsor
Sponsorship breakdown
Export CSV (upgrade) →1 sponsors · 5 co-sponsors · 247 not signed on
Sponsors (1)
- Nathan Davidson Democratic
Co-sponsors (5)
- RIVERA
- Perry A. Stambaugh Republican
- Manuel Guzman Democratic
- Chris Pielli Democratic
- Joseph C. Hohenstein Democratic
Not signed on (247)
247 members have not signed on to this bill.
Show all 247 →"Not signed on" means a member has not sponsored or co-sponsored this bill — it does not imply opposition. Members flagged Voted No have a recorded No vote on this bill.
Subjects
Frequently asked questions
- What does HB 2880 do?
- Cutting Costs and Expanding Access to Customer-Owned Energy
- Who sponsors HB 2880?
- HB 2880 is sponsored by RIVERA, Nathan Davidson (Democratic), Perry A. Stambaugh (Republican), Manuel Guzman (Democratic), Chris Pielli (Democratic), and Joseph C. Hohenstein (Democratic).
- What is the current status of HB 2880?
- This bill is in committee in the House. Introduced October 21, 2026. It must pass committee before a floor vote.
- Where can I track HB 2880?
- Track HB 2880 free on One Click Politics — get push/email alerts when it moves.
Make your voice heard on HB 2880
Find the representatives who decide this bill and tell them where you stand — for yourself, or mobilize your whole list in one click with One Click Politics advocacy software.
Stay ahead of HB 2880
Last checked for changes 1 day ago · updated continuously
One Click Politics tracks every bill in Congress and all 50 states.
Track this bill →