F L O R I D A H O U S E O F R E P R E S E N T A T I V E S CS/CS/HB741 2022 A bill to be entitled An act relating to net metering;
F L O R I D A H O U S E O F R E P R E S E N T A T I V E S CS/HB741 2022 A bill to be entitled An act relating to net metering;
providing the terms for public utility net metering programs after a specified date;
revising and providing legislative findings relating to the redesign of net metering to avoid cross-subsidization of electric service costs between classes of ratepayers;
providing a schedule of reductions to net metering rate designs that apply to customers with net metering applications that are approved after specified dates;
requiring the Public Service Commission to propose new net metering rules that comply with specified criteria by a certain date;
authorizing certain customers who own or lease renewable generation to remain under the net metering rules that initially applied to those customers for a specified time;
authorizing certain customers who own or lease renewable generation before a specified date to remain under the existing net metering rules for a specified time;
authorizing public utilities to petition for approval of certain fixed charges designed to meet specified purposes;
providing conditions under which rules must be initiated if the penetration rate of customer-owned or leased renewable generation meets a specified threshold;
authorizing public utilities to recover specified lost revenues upon meeting certain requirements;
requiring certain public utilities to provide a specified report to the commission;
Subsection (5) of section 366.91, Florida Statutes, is amended to read:
Subsections (6) through (9) of section 366.91, Florida Statutes, are renumbered as subsections (7) through (10), respectively, subsections (1) and present (7) of that section are amended, and a new subsection (6) is added to that section, to read:
366.91 Renewable energy.— Page 1of 7 CODING:
366.91 Renewable energy.— (1) The Legislature finds that:
(a) It is in the public interest to continue promote the Page 1of 4 CODING:
hb0741-02-c2 F L O R I D A H O U S E O F R E P R E S E N T A T I V E S CS/CS/HB741 2022 (5)(a) On or before January 1, 2009, Each public utility shall develop a standardized interconnection agreement and net metering program for customer-owned or leased renewable generation.
hb0741-01-c1 F L O R I D A H O U S E O F R E P R E S E N T A T I V E S CS/HB741 2022 development of renewable energy resources in this state in a manner that is fair and equitable to all public utility customers.
The commission shall establish requirements relating to the expedited interconnection and net metering of customer- owned or leased renewable generation by public utilities and shall may adopt new rules to administer this section.
Renewable energy resources have the potential to help diversify fuel types to meet Florida's growing dependency on natural gas for electric production, minimize the volatility of fuel costs, encourage investment within the state, improve environmental conditions, and make Florida a leader in new and innovative technologies.
(b) Effective January 1, 2024, public utility net metering programs for customer-owned or leased renewable generation must provide that:
The development and maturation of the solar energy industry, the substantial decline in the cost of solar panels, and the increase in customer-owned and leased renewable generation support the redesign of net metering by the commission.
1.
(b) Customer-owned and leased renewable generation are not available to many public utility customers who lack the financial resources to purchase or lease rooftop solar panels or who reside in multitenant buildings.
Electricity used by the customer in excess of the generation supplied by customer-owned or leased renewable generation is billed by the public utility in accordance with normal billing practices;
The substantial growth of customer-owned and leased renewable generation has resulted in increased cross-subsidization of the full cost of electric service onto the public utility's general body of ratepayers.
and 2.
Therefore, the redesigned net metering rate structures required in paragraph (6)(a) must ensure that public utility customers who own or lease renewable generation pay the full cost of electric service and are not cross-subsidized by the public utility's general body of ratepayers.
Excess customer-owned or leased renewable generation delivered to the public utility's electric grid during the customer's regular billing cycle is credited to the customer's energy consumption for the next month's billing cycle as follows:
(6)(a) On or before January 1, 2023, the commission shall Page 2of 4 CODING:
a.
For energy credits produced from customer-owned or leased renewable generation for which a net metering application is approved between January 1, 2024, and December 31, 2025, the customer's energy usage is offset by 75 percent of the amount credited;
b.
For energy credits produced from customer-owned or Page 2of 7 CODING:
hb0741-02-c2 F L O R I D A H O U S E O F R E P R E S E N T A T I V E S CS/CS/HB741 2022 leased renewable generation for which a net metering application is approved between January 1, 2026, and December 31, 2026, the customer's energy usage is offset by 60 percent of the amount credited;
hb0741-01-c1 F L O R I D A H O U S E O F R E P R E S E N T A T I V E S CS/HB741 2022 propose a revised net metering rule that complies with the following criteria:
and c.
For energy credits produced from customer-owned or leased renewable generation for which a net metering application is approved between January 1, 2027, and December 31, 2028, the customer's energy usage is offset by 50 percent of the amount credited.
(c) A public utility customer who owns or leases renewable generation for which a net metering application is approved before January 1, 2029, pursuant to a standard interconnection agreement offered by a public utility, is granted 20 years to continue to use the net metering rate design and rates that applied at the time the net metering application was approved.
This paragraph applies to customers who purchase or lease real property upon which customer-owned or leased renewable generation is installed for all or part of that 20-year period.
(d) On or after the effective date of the net metering programs described in paragraph (b), a public utility may petition the commission for approval to impose any combination of fixed charges, which may include base facilities charges, electric grid access fees, and monthly minimum bills, to ensure that the public utility recovers the fixed costs of serving customers that own or lease renewable generation and that the Page 3of 7 CODING:
Words strickenare deletions;
words underlined are additions.
hb0741-02-c2 F L O R I D A H O U S E O F R E P R E S E N T A T I V E S CS/CS/HB741 2022 general body of public utility ratepayers do not subsidize customer-owned or leased generation.
Within 180 days after a petition is filed by a public utility pursuant to this paragraph, the commission must issue a final order on the petition.
(e) The commission must adopt new rules to become effective January 1, 2029, that establish a new program design for customer-owned or leased renewable generation for which a net metering application is approved on or after January 1, 2029.
The new program design must comply with the following criteria:
Each public utility customer who owns or leases renewable generation must pay the full cost of electric service and may not be subsidized by the public utility's general body of ratepayers.
The net metering rate structures and billing must ensure that public utility customers owning or leasing renewable generation pay the full cost of electric service and are not subsidized by the public utility's general body of ratepayers.
All energy delivered by the public utility must be purchased at the public utility's applicable retail rate and all energy delivered by the customer-owned or leased renewable generation to the public utility must be credited to the customer at the public utility's full avoided costs.
The net metering must ensure that all energy delivered by the public utility is purchased at the public utility's applicable retail rate and that all energy delivered by the customer-owned or leased renewable generation to the public utility is credited to the customer at the public utility's full avoided costs.
(f)1.
3.
If at any time the penetration rate of customer- owned or leased renewable generation in a public utility's service territory is reasonably expected to exceed 6.5 percent within the succeeding 12 months, the commission, upon petition or on its own motion, must initiate rulemaking to adopt a new Page 4of 7 CODING:
The net metering may include fixed charges, including base facilities charges, electric grid access fees, or monthly minimum bills, to help ensure that the public utility recovers the fixed costs of serving customers who engage in net metering and that the general body of public utility ratepayers do not subsidize customer-owned or leased generation.
(b) Any public utility customer who owns or leases renewable generation that is in service before January 1, 2023, pursuant to a standard interconnection agreement offered by a public utility, shall be granted 20 years to continue to use the net metering rate design and rates that applied before the revised net metering rule was adopted under paragraph (a).
This paragraph applies to customers who purchase or lease real Page 3of 4 CODING:
Show all 78 changed rows (38 more)
Previous
Latest
hb0741-02-c2 F L O R I D A H O U S E O F R E P R E S E N T A T I V E S CS/CS/HB741 2022 program design that complies with subparagraphs (e)1.
hb0741-01-c1 F L O R I D A H O U S E O F R E P R E S E N T A T I V E S CS/HB741 2022 property upon which customer-owned or leased renewable generation is installed for all or part of that 20-year period.
and 2.
(c) The commission shall require a public utility requesting a change in base rates under s.
A new program design adopted pursuant to this subparagraph becomes effective 60 days after rule adoption or 60 days after the date the commission determines that the actual penetration rate has reached 6.5 percent, whichever is later, and shall apply to customer-owned or leased renewable generation for which a net metering application is approved after that effective date.
366.06 to report to the commission the impact of net metering on the public utility's revenues and cost of service.
2.
(8)(7) Under the provisions of subsections (5) and (7)(6), when a utility purchases power generated from biogas produced by the anaerobic digestion of agricultural waste, including food waste or other agricultural byproducts, net metering shall be available at a single metering point or as a part of conjunctive billing of multiple points for a customer at a single location, so long as the provision of such service and its associated charges, terms, and other conditions are not reasonably projected to result in higher cost electric service to the utility's general body of ratepayers or adversely affect the adequacy or reliability of electric service to all customers, as determined by the commission for public utilities, or as determined by the governing authority of the municipal electric utility or rural electric cooperative that serves at retail.
For purposes of this paragraph, the penetration rate shall be calculated by dividing the total summer peak demand of the public utility by the aggregate gross power rating (alternating current) of all in-service customer-owned or leased renewable generation in the public utility's service territory.
(g) This subsection establishes the minimum requirements for each public utility net metering program.
A public utility may petition the commission at any time for approval to offer a net metering program on terms that are not less favorable to customers who own or lease renewable generation than the terms specified in this subsection or in commission rules adopted pursuant to this subsection.
(h)1.
A public utility may recover, through its fuel and purchased power cost recovery charge, its lost revenues resulting from the incremental addition of residential customer- owned or leased solar photovoltaic generation within the public utility's service territory between July 1, 2022, and December 31, 2023, above the level that such generation, for purposes of Page 5of 7 CODING:
Words strickenare deletions;
words underlined are additions.
hb0741-02-c2 F L O R I D A H O U S E O F R E P R E S E N T A T I V E S CS/CS/HB741 2022 setting base rates in the public utility's most recent base rate proceeding, was estimated to be installed within the public utility's service territory during the same period.
2.
A public utility seeking recovery of lost revenues under this paragraph must file with the commission a petition that:
a.
Identifies the total capacity of residential customer- owned or leased solar photovoltaic generation that, for purposes of setting base rates in the public utility's most recent base rate proceeding, was estimated to be installed in the public utility's service territory between July 1, 2022, and December 31, 2023;
b.
Identifies the total capacity of residential customer- owned or leased solar photovoltaic generation that was installed in the public utility's service territory between July 1, 2022, and December 31, 2023;
c.
Demonstrates the difference in revenues collected by the public utility as a direct result of the incremental difference in the estimated and actual capacity additions identified in sub-subparagraphs a.
and b.
and identifies the specific amount that the utility seeks to recover;
d.
Demonstrates that the relief requested does not cause the public utility to exceed the rate of return on equity authorized by the commission in the public utility's most recent base rate proceeding;
and Page 6of 7 CODING:
Words strickenare deletions;
words underlined are additions.
hb0741-02-c2 F L O R I D A H O U S E O F R E P R E S E N T A T I V E S CS/CS/HB741 2022 e.
Includes such other reasonably related information as the commission may require by rule.
3.
Upon receipt of a petition that meets the requirements of subparagraph 2., the commission must determine the amount, if any, that the utility is entitled to recover under this paragraph.
4.
A petition filed under this subsection may not be filed before December 31, 2023, or after March 31, 2024.
5.
The Legislature provides the limited, extraordinary relief set forth in this paragraph to address the potential impact on a public utility of a previously unanticipated surge, unaccounted for in the utility's last rate case, in the installation of customer-owned or leased renewable generation over the period specified in this subsection.
The Legislature makes no findings as to whether the recovery of lost revenues by a public utility is appropriate for any other purpose.
Page 7of 7 CODING:
Page 4of 4 CODING:
hb0741-02-c2
hb0741-01-c1
⬇ Download PDF